Zhonghua Xinnet news: Recently, organized by the project management department of the ethylene project in Henan, the construction of the road network and the water supply and drainage network (including the fire water network) for the million-ton ethylene project is progressing steadily.

The total length of the road construction in the ethylene plant area is approximately 22,800 meters, and the diameter of the water supply and drainage network (including the fire water network) ranges from 100 to 2400 millimeters, with a total length of about 112,700 meters. The total investment in the project is approximately 190 million yuan, divided into five sections, covering key areas of the plant's infrastructure construction.
An improved factory area road network can ensure efficient and smooth transportation of goods and personnel, while a scientifically laid out water supply and drainage network can provide strong support for safe production and environmentally friendly operations of the project. On June 27, the excavation work for the North China Road foundation pit began, and then construction teams for various sections entered the site one after another, with the preparation of construction equipment and materials proceeding in an orderly manner.
Currently, construction on the five sections of the project has fully commenced. All participating units are strengthening safety, environmental protection, and quality management, steadily advancing according to the established plan, with the aim of completing the work before the Spring Festival in 2026.
Source: China Chemical News